Week of April 17, 2017
US 141 and Tyler Rd… Pavement Removal, Sanitary Sewer/Water Main Construction.
US 141 Main St. to Brook St…. Temporary water set up and dewatering well installation, Pavement Removal.
Landscape and Driveway restoration of 2016 areas will commence based on dry weather conditions.
Phase 1 – Main St. to Hill St.
Sanitary Sewer & Water Main: Done
Landscape Restoration: May 1st – May 15th, weather dependent.
Phase 2 – Hill St. to Vine St./Tyler Rd.
Sanitary Sewer & Water Main: April 17th – May 1st.
Landscape Restoration: May 1st – May 30th.
Phase 3 – Main St. to Brook St./Clark St.
Sanitary Sewer and Water Main: May 1st – May 21st.
Landscape Restoration: May 21st – June 15th.
Phase 4 – Brook St. to Pine St.
Sanitary Sewer and Water Main: May 21st – June 15th.
Landscape Restoration: June 1st. – June 21st.
Phase 5 – West Main St.
Sanitary Sewer and Water Main: Done
Landscape Restoration: May 1st. – May 15th, weather dependent.
For future construction information, check out the City of Niagara website:
www.cityofniagara.org